Manchester Road Streetscape Phase 2

Most recent view of Manchester Road
Project Updates
November 15, 2013
This project has been completed. 

October 28, 2013
Sodding work has been completed and street trees are being planted this week, which will complete this project.
 
July 15, 2013
Paving operations are scheduled to begin on Tuesday, July 16. Motorists should expect delays for the remainder of the week as crews place the new asphalt pavement. Please consider alternate routes if possible for the next few days.

June 21, 2013
Marschuetz has completed most of the sidewalks and concrete work. The electrical subcontractor has begun working on installing the street light conduits and light poles and should complete most of their work by mid-July. Asphalt operations should begin after the lighting contractor is finished in mid-July.

Please continue to use caution while traveling through this area.

May 30, 2013
Marschuetz has completed most of the curb and new sidewalk along Manchester Road. The contractor should begin working on installing the street light conduits and light poles in June. Asphalt operations should begin in late June or early July.

Please continue to use caution while traveling through this area.

April 23, 2013
The remaining Missouri American Water Company relocation work in East Avenue has been completed and the storm sewer has been installed under East Avenue. Marschuetz has placed some of the new sidewalk along the east edge of Rte. 109 and some of the sidewalk along the south side of Manchester Road on the east end of the project. They also began excavation for the curb and sidewalk work on the very west end of the project. Work will continue on the curb & gutter and sidewalks as weather allows. The contractor should begin working on installing the street light conduits and light poles next month.

Please continue to use caution while traveling through this area.

March 25, 2013
All of the utility relocation work has been completed except for one remaining Missouri American Water Company conflict in East Avenue. Missouri American will be on site over the next few weeks, weather permitting, to complete this final relocation. Marschuetz has been able to complete all of the storm sewer installation except for the run under East Avenue and will complete that run after Missouri American has relocated their water line. Marschuetz has also been able to complete much of the curb and gutter work in the meantime, as well as some of the new concrete approaches and driveways. They will continue on this work as weather allows and begin sidewalk work over the next month.

Please continue to use caution while traveling through this area.

January 15, 2013
The city's contractor, J.M. Marschuetz Construction, has begun Phase 2 of the Manchester Road Streetscape project. This project will include new curbs, sidewalks, street lights, trees, and pavement on Manchester Road from Route 109 to Eatherton Road. Most of the work over the next two months will involve relocating various utilities that are in conflict with underground drainage structures. Laclede will be relocating gas lines at various locations, as will Missouri American Water Company. Much of the relocation work will be at the intersection with Center Avenue and also at the rock culvert crossing near the Metro West Fire Station.

Please use caution while traveling through this area during these improvements.