Strecker Road Bridge Replacement

May 14, 2019

The City's contractor, Gershenson Construction, will close Strecker Road at 7:00 am on May 28 to begin this project.  Ameren crews will be on site performing some utility relocation work over the next few weeks in preparation for the bridge replacement.  Electronic message boards were placed at the bridge location to notify motorists of the upcoming closure.  The closure is expected to be in place until late August.  Motorists will need to use the signed detour route along Clayton and Valley Roads for the duration of the closure.

Project Overview

This project will replace the bridge on Strecker Road over Caulks Creek located between Wildwood Meadows Court and Quaethem Drive.  Strecker Road will be closed at the project site for approximately ninety (90) days to construct this project.  A signed detour route will be in place using Clayton Road and Valley Road.