Future Capital Improvement Projects


Strecker Road Sidewalk Project, Ward 2 and Ward 4)

The goal of this project is to provide a continuous sidewalk along Strecker Road between Clayton Road to the Ellisville City Limit. Design of this project is underway. The first phase of the project will construct an 850’ long segment of sidewalk from Englebrook Drive to the east.

  • Budgeted Construction Cost = $105,000 (2020)
  • Budgeted Right of Way Cost = $20,000 (2020)
  • Planned Construction Year = 2020

Manchester Road Shared Use Path (Ward 1) 

This project will construct a 10’ wide shared use path along Manchester Road between Route 109 to Pond Road.  The City was awarded federal funding for this project. Negotiations for easement acquisition is underway now. 

  • Budgeted Construction Cost = $1017,000 = $508,500 City + $508,500 Federal
  • Budgeted Right of Way Cost = $100,000 (2020)
  • Planned Construction Year = 2021

Woods Road Flood Mitigation Project (Ward 6)

The City will reduce the occurrence of flooding on Woods Avenue between State Route 109 and Manchester Road. The project will remove and replace several existing hydraulically deficient culverts and improve the channel. 

  • Budgeted Construction Cost = $225,000 (2021)
  • Budgeted Final Design Cost = $50,000 (2020)
  • Planned Construction Year = 2021

Birch Forest Drive Turn Around (Ward 5)

This project will remove the existing temporary asphalt cul-de-sac located at the end of Birch Forest Drive (West) and replace it with a T-Turnaround. 

  • Budgeted Construction Cost = $75,000 (2021)
  • Planned Construction Year = 2021

Bouquet Road Culverts #340 and #352 Replacement (Ward 6)

This project will remove and replace two existing structurally deficient concrete box culverts under Bouquet Road. 

  • Budgeted Construction Cost = $800,000
  • Budgeted Right of Way Cost = $20,000
  • Planned Construction Year = 2022

Manchester Road and Taylor Road Resurfacing and Traffic Signal Improvement Project (Ward 7 and Ward 8)

This project will upgrade the City’s three traffic signals (Manchester Road at Pierside Lane, Manchester Road at Schnucks Wildwood Crossing, and Taylor Road at Main Street) as well as resurface Taylor Road from Manchester Road to Route 100 and resurface Manchester Road from east of Old Fairway to Route 100. Design of this project is underway.  The city is expecting to receive federal funds to construct the project. 

  • Budgeted Construction Cost = $1,000,000 ($200,000 City + $800,000 Federal) 2022
  • Planned Construction Year = 2022

Center Avenue Reconstruction (Ward 8)

This project will resurface and widen Center Avenue from Manchester Road to Bordeaux Estates Ct./Falstone Mill Ct. 

  • Budgeted Construction Cost = $300,000
  • Planned Construction Year = 2022-23 

Eatherton Road Improvement Project (Ward 8)

The City is designing improvements to Eatherton Road from Manchester Road to Cambury Lane. The improved road is proposed to include a sidewalk (along the west side), 10’ trail (along the east side), storm sewers, and lighting.  

  • Budgeted Construction Cost = $2,300,000
  • Budgeted Right of Way Cost = $150,000 (2022)
  • Budgeted Final Design Cost = $75,000 (2020)
  • Planned Construction Year = 2023 

Bridge 387 Replacement (Ward 1)

This project will prepare remove and replace Bridge #387 over Wildhorse Creek on Wild Horse Creek Road.  The city received federal funding for this project.

  • Budgeted Construction Cost = $1,700,000 ($340,000 City + $1,360,000 Federal) 2023
  • Budgeted Right of Way Cost = $30,000 (2022)
  • Budgeted Final Design Cost = $150,000 (2020)
  • Planned Construction Year = 2023 

Alt Road Flood Mitigation Project (Ward 6)

This project will re-build and raise a section of Alt Road at State Route 109 to provide flood free access. 

  • Budgeted Construction Cost = $500,000
  • Budgeted Right of Way Cost = $15,000
  • Planned Construction Year = 2023 

Bridge 385 and 386 Replacements (Ward 1)

This project will replace Bridges #385 over a tributary of Wildhorse Creek on Ossenfort Road and Bridge #386 over Wildhorse Creek at Ossenfort Road. 

  • Budgeted Construction Cost = $850,000 (2024)
  • Budgeted Right of Way Cost = $30,000 (2023)
  • Planned Construction Year = 2024 

Route 109 Sidewalk Improvement Project (Ward 8) 

This project will construct sidewalk along the east side of Route 109 from Manchester Road to Viola Gill Lane.

  • Budgeted Construction Cost = $0
  • Planned Construction Year =TBD